Karnataka RERA for Homebuyers: Checking Projects, Delay Interest, Refunds, Complaints, Recovery Certificates and Appeals
Real estate projects in Bengaluru and the rest of Karnataka are regulated by the Karnataka Real Estate Regulatory Authority (K-RERA) under the Real Estate (Regulation and Development) Act, 2016. Projects on land above 500 sqm or with more than eight units must be registered before they are advertised or sold. If a builder fails to hand over possession by the date in the agreement, a buyer can either withdraw and claim a refund with interest, or stay in the project and claim interest for every month of delay. K-RERA orders that are not paid are sent for recovery as arrears of land revenue through the district administration, a step that has often been slow in Bengaluru. This guide explains how to use RERA effectively.
Project registration and checks
| Check | Where |
|---|---|
| RERA registration number and validity | K-RERA portal |
| Approved plans, number of units and carpet areas | Project documents uploaded on the portal |
| Promised completion date | Registration details |
| Quarterly progress updates | Portal |
| Litigation and complaints against the project | Portal and court searches |
| Builder’s other projects and track record | Portal |
Projects split into small phases to avoid the threshold, or advertised before registration, are warning signs.
Your key rights under RERA
- Advance limit: the builder cannot take more than 10% of the price before a registered agreement for sale.
- Carpet area pricing: the price must be based on carpet area, as defined.
- Possession: delivery on the agreed date, with the occupancy certificate.
- Delay remedies: refund with interest, or interest for each month of delay.
- Structural defects: rectification of defects reported within five years of possession.
- Common areas: transfer to the association; see our apartment association guide.
Complaint process
- File online on the K-RERA portal with the agreement, payment receipts, correspondence and the relief sought.
- Pay the fee.
- Hearings before the Authority; many are now online.
- Order for refund, interest or directions.
- Compensation claims are decided by the adjudicating officer.
- Appeals lie to the Karnataka Real Estate Appellate Tribunal, and then to the High Court on questions of law.
Recovery when the builder does not pay
If the builder does not comply, K-RERA issues a recovery certificate to the Deputy Commissioner to recover the amount as arrears of land revenue. Buyers should follow up with the DC’s office, identify the builder’s assets (unsold units, bank accounts), and where the builder is insolvent, file claims in insolvency proceedings. Homebuyers’ associations often act together to push recovery.
Example
A buyer booked a 2BHK in a RERA-registered project in Thanisandra for ₹70 lakh, with possession promised in March 2025. By mid-2026, construction is stalled. The buyer files a complaint and seeks a refund with interest. K-RERA orders the builder to refund the amount paid with interest at the prescribed rate. The builder does not pay, so a recovery certificate is issued. The buyer and 40 other buyers jointly follow up with the Bengaluru Urban DC’s office, which attaches unsold units for recovery.
Agreement for sale under RERA
- Check that the agreement follows the model terms in the Karnataka RERA rules.
- Possession date, specifications, carpet area and payment schedule linked to construction stages must be clear.
- Register the agreement and pay the applicable stamp duty; see our stamp duty guide.
Practical tips for Bengaluru buyers
- Pay only against construction milestones you can verify on site and on the portal.
- Keep all communication in writing.
- Join or form a buyers’ group early in a delayed project.
- Check the builder’s GST invoices and the rate charged; see our GST on flats in Bengaluru guide.
- Before booking, run the full document check in our Bengaluru flat buying checklist.
Tax on RERA awards
| Amount received | Tax treatment (generally) |
|---|---|
| Refund of principal | Not income |
| Interest on refund or for delay | Taxable as interest income in the year received, subject to the facts |
| Compensation for mental agony or specific losses | Treatment depends on nature; take advice |
| Interest received while continuing in the project | Taxable as income, or in some views reduces cost; take advice |
Keep RERA orders and payment details for your return.
For promoters
Promoters must register projects, maintain the separate account with 70% of collections, upload quarterly updates, get annual audits of project accounts, and comply with orders. Penalties for non-registration and non-compliance can be a percentage of the project cost.
Buyers’ associations
Buyers in delayed projects often form an association to pursue complaints together, share legal costs and negotiate with the builder or lenders. Collective action also helps in insolvency proceedings, where homebuyers are financial creditors.
Possession with defects
If possession is offered with defects, record them in writing at handover and ask for rectification under the five-year defect liability provision.
FAQs
Which projects must register with Karnataka RERA?
Projects on land above 500 sqm or with more than eight units, including all phases, unless exempt.
Can I get a refund if my Bengaluru flat is delayed?
Yes. You can withdraw and claim a refund with interest, or stay and claim interest for the delay.
What if the builder does not pay the RERA order?
K-RERA issues a recovery certificate to the Deputy Commissioner for recovery as arrears of land revenue.
Can I approach the consumer commission instead of RERA?
Yes, homebuyers can choose consumer forums for deficiency in service; RERA is often faster for delay and refund claims against registered projects.
Is there a time limit to file a RERA complaint?
RERA does not prescribe a short limitation period for complaints, but file promptly to strengthen your claim.
TAXAJ, with its office in J.P. Nagar, Bengaluru, supports homebuyers with RERA filings through its legal team and handles the tax on refunds and interest. Talk to our Bengaluru team.
Last updated 11 November 2026. Sources: Real Estate (Regulation and Development) Act, 2016, sections 3, 4, 13, 18, 19, 31, 40 and 43; Karnataka Real Estate (Regulation and Development) Rules, 2017; K-RERA portal. The example is illustrative. General information only.