TG-iPASS: How Industrial Approvals Work in Telangana for Factories and Large Projects
Telangana’s industrial approvals run through TG-iPASS, the single window system created by the Telangana State Industrial Project Approval and Self-Certification System Act, 2014. Investors file one common application for multiple state clearances, such as factory plan approval, pollution consent, building permission and power connection, on the basis of self-certification. The law sets time limits for approvals, provides for deemed approval if departments do not act and gives investors a right to know the reasons for any delay. Manufacturing projects in Telangana, from pharmaceuticals in Genome Valley to food processing and electronics, typically use this route. This guide explains how it works.
What TG-iPASS covers
| Clearance | Department (typical) |
|---|---|
| Land allotment in industrial parks | TGIIC |
| Building or layout permission | Municipal or HMDA/DTCP authority |
| Consent to establish and operate | Pollution Control Board |
| Factory plan approval and licence | Factories department |
| Power connection | Electricity distribution company |
| Fire NOC | Fire services |
| Water connection | Water board or irrigation |
| Registrations under labour laws | Labour department |
The exact list depends on the project.
Timelines and deemed approval
The 2014 law sets maximum timelines for approvals, with shorter timelines for mega projects above a specified investment. If a department does not decide within the time, the approval is deemed to be given, subject to conditions. Investors can track applications online. In practice, complete documents and a well-prepared self-certification avoid most delays.
Steps for a new manufacturing unit
- Incorporate the company or LLP and obtain PAN and TAN. See our Telangana company registration page.
- Prepare a project report with investment, employment and products.
- Identify land, either in a TGIIC park or private land with correct land use.
- File the common application on TG-iPASS with self-certification.
- Obtain consent to establish before starting construction.
- Build and install machinery; register under labour laws.
- Obtain consent to operate and the factory licence.
- Start commercial production and apply for incentives within time.
Land
TGIIC develops industrial parks and allots land on lease or sale under its policies. Private land must have the correct land use and, for agricultural land, conversion. Check the land on Bhu Bharati and the master plan. See our guide on Bhu Bharati land records.
Incentives
Telangana’s industrial incentive schemes have offered investment subsidies, reimbursement of stamp duty and land conversion charges, power cost reimbursement, interest subsidies and SGST reimbursement for eligible units, with additional support for SC/ST and women entrepreneurs and for MSMEs. Eligibility, rates and time limits depend on the policy in force when the unit starts. Apply within the claim period and keep proof of each condition. See our guide on MSME schemes in Telangana.
Tax points
- Capital subsidies reduce the cost of assets for depreciation if linked to specific assets, or may be taxed as income depending on their nature.
- SGST reimbursements received as incentives are generally treated as income unless they meet conditions for capital receipts; take advice.
- New manufacturing companies: a concessional corporate tax regime was available for companies starting manufacturing before a cut-off date; existing companies can use the 22% regime without incentives.
- GST: claim input tax credit on plant and machinery; credit on factory building construction is blocked.
Example
A pharma startup plans an API unit near Hyderabad with ₹40 crore investment. It incorporates a private limited company, takes a plot in an industrial park, files on TG-iPASS and receives consent to establish. After construction, it obtains the factory licence and consent to operate, registers for GST and drug licences, starts production and files incentive claims. See our guide on pharma company compliance in Hyderabad.
Common mistakes
- Starting construction before consent to establish.
- Buying agricultural land without checking conversion and land use.
- Missing incentive claim deadlines.
- Treating incentives as capital receipts without analysis.
- Ignoring post-commissioning compliance such as annual returns under labour and pollution laws.
Self-certification responsibilities
Under TG-iPASS, the investor certifies that the project meets the rules for the approvals sought. Inspections may happen later. False certification can lead to cancellation of approvals and penalties, so involve qualified engineers, architects and consultants.
Industrial parks and clusters near Hyderabad
Industrial activity around Hyderabad is spread across clusters for pharmaceuticals, life sciences, electronics, food processing, aerospace and general engineering, many developed by TGIIC. Location affects land cost, incentives, power supply and logistics. Compare options with a full cost model, including approvals and time.
After commissioning
Once operating, units file annual returns under factory, pollution and labour laws, renew licences, maintain safety records and keep GST, income tax and company filings current. Incentive claims often require proof of continued operation and employment.
Expansion and change of product
Existing units adding capacity, new products or new locations may need fresh or amended approvals, including consent to establish for expansion. Apply through the single window before starting work, and update factory licences, GST registration and incentive eligibility. Expansion projects can sometimes qualify for incentives as substantial expansion under state policies.
FAQs
What is TG-iPASS?
Telangana’s industrial single window clearance system under the 2014 self-certification law.
Is there deemed approval under TG-iPASS?
Yes, the law provides for deemed approval when departments do not act within the timelines, subject to conditions.
Does TG-iPASS cover building permission for factories?
Yes, building permission is among the clearances that can be processed.
Can MSMEs use TG-iPASS?
Yes, the system covers projects of all sizes, with different timelines.
Are incentives automatic?
No. Units must apply within the time limits and meet the conditions.
Can a unit start trial production before consent to operate?
Trial runs need the permissions specified by the pollution control board; check the consent conditions.
Does TG-iPASS cover pollution clearances?
Yes, consent to establish and operate are processed through the single window.
Is TG-iPASS available for service businesses?
It mainly covers industrial projects; other businesses use sector-specific approvals.
TAXAJ helps manufacturers in Telangana with incorporation, GST, incentive accounting and annual compliance, from our Bengaluru branch and online. See our Telangana company registration and compliances page.
Last updated 11 November 2026. Sources: Telangana State Industrial Project Approval and Self-Certification System Act, 2014; Telangana industrial policy and incentive guidelines; Income-tax law on subsidies and concessional regimes; GST law on blocked credit. The example is illustrative. General information only; confirm current policies.