Gujarat Renewable Energy Policy for Solar, Wind and Hybrid Projects: Captive Use, Open Access, Banking, Khavda and Tax
Gujarat has one of India’s largest renewable energy portfolios and an integrated renewable energy policy covering solar, wind, hybrid and storage projects. Businesses can set up projects for captive use, group captive use, sale to DISCOMs or third-party sale through open access, with banking of surplus energy as per the policy and GERC regulations. Large parks such as Khavda in Kutch host gigawatt-scale projects. Developers need land, connectivity and approvals from GEDA and the transmission utility. GST on solar devices was reduced in the 2025 rationalisation, and investors claim depreciation on plants. This guide gives an overview; check the current policy and regulations.
Project types
| Type | Who uses it |
|---|---|
| Captive | Industrial units consuming their own generation |
| Group captive | Multiple consumers with equity in the project |
| Third-party sale | Developers selling to consumers via open access |
| Sale to DISCOMs | Through tenders and PPAs |
| Rooftop | Consumers on their premises. See our rooftop solar guide |
Key policy features (check current terms)
- Capacity limits relative to sanctioned demand for some categories.
- Banking of energy with charges.
- Open access charges and any exemptions.
- Cross-subsidy surcharge and additional surcharge as per regulations.
- Hybrid and storage support.
Land
- Government land in parks, including Khavda, allotted to developers.
- Private land leased or purchased, with NA permission. See our NA guide.
- Lease rentals to farmers for wind turbines.
Approvals
- Registration with GEDA.
- Connectivity from the transmission utility.
- Approvals from the electrical inspector.
- Environmental and forest clearances where needed.
Tax and GST
| Item | Treatment |
|---|---|
| Solar modules and devices | Concessional GST after 2025 changes |
| EPC contracts | Value split as notified |
| Depreciation | At applicable rates for plant |
| Electricity sales | Electricity is exempt from GST |
| Input tax credit | Since electricity is exempt, credit on inputs may be blocked for generators selling power |
Financing
Developers raise loans, green bonds and equity. Some list green bonds on GIFT City exchanges. See our guide on listing on GIFT City exchanges.
Example
A Vapi chemical company sets up a 25 MW solar project in north Gujarat for captive use through open access, with banking of surplus. It registers with GEDA, gets connectivity and pays open access charges. It claims depreciation on the plant. Its power cost falls compared with grid tariffs.
Wind projects
Gujarat’s coastline has strong wind potential. Wind projects need land leases, micro-siting approvals, connectivity and environmental checks. Repowering old turbines with new ones is also supported under policy provisions.
Hybrid and storage
Hybrid wind-solar projects use land and transmission efficiently. Battery storage helps manage peak demand. Policies support these with specific provisions.
Green hydrogen and green ammonia
Gujarat is attracting green hydrogen projects in Kutch and coastal areas, linked to renewable capacity. Land, water and incentives are key considerations.
Tax on project companies
Project companies (SPVs) choose tax regimes, plan depreciation and handle GST on EPC contracts. Long-term PPAs give stable income. Transfer pricing applies to related-party EPC or O&M contracts.
Carbon credits
Projects may earn carbon credits. Income from transfer of carbon credits is taxed at a concessional rate under specific provisions; check current law. GST on carbon credit trading should be checked.
Risks
- Grid curtailment.
- Changes in open access charges.
- Land disputes.
- Delays in payments by DISCOMs.
Steps for a captive project
- Assess consumption and load profile.
- Choose site and technology.
- Register with GEDA.
- Apply for connectivity and open access.
- Arrange financing.
- Construct and commission.
- Start banking and settlement.
Key takeaways
- Choose the right model: captive, group captive, third party or PPA.
- Register with GEDA and secure connectivity.
- Understand open access and banking charges.
- Plan depreciation and GST.
- Track policy and regulation changes.
A worked example
A textile mill in Surat joins a group captive wind-solar hybrid project in Kutch, buying a small equity stake and consuming power through open access. It pays open access and banking charges, saves on grid tariffs and accounts for its equity investment. The SPV claims depreciation on the plant.
Rooftop or ground-mounted?
Rooftop systems suit factories with large sheds and limited power needs, while ground-mounted projects via open access suit larger consumers. Compare costs, land, charges and contract terms before choosing.
FAQs
Can industries set up captive solar in Gujarat?
Yes, under the renewable energy policy.
What is banking of energy?
Storing surplus energy with the grid for later use, with charges.
What is Khavda?
A large renewable energy park in Kutch.
Is GST payable on electricity?
No, electricity is exempt.
Can I sell solar power to other companies?
Yes, through third-party sale under open access rules.
Who registers renewable projects?
GEDA.
Is repowering of old wind turbines supported?
Yes, under policy provisions.
Are carbon credits taxable?
Yes, at a concessional rate under specific provisions; check current law.
Is green hydrogen being developed in Gujarat?
Several projects are planned in Kutch and coastal areas.
What is the first step for a captive renewable project?
Assess consumption and load profile.
Can group captive projects share power?
Yes, among consumers with equity in the project.
Can a mill join a group captive project?
Yes, by holding equity and consuming as per rules.
Can farmers lease land for solar?
Yes, with appropriate agreements and permissions.
Is wind energy part of the policy?
Yes.
TAXAJ helps renewable energy investors with structuring, tax and financing compliance, serving Gujarat online from our offices in Delhi, Bengaluru and Goa. See our guide on Gujarat industrial incentives.