Land Conversion Sanad in Goa (2026): Section 32 Process, the New 45-Day Limit, Change of Zone and Common Rejections
Before you can build a house, villa project or hotel on land in Goa, the land must be permitted for non-agricultural use. That permission is a conversion sanad granted by the Collector (or the officer delegated) under section 32 of the Goa Land Revenue Code, 1968, based on reports from the Town and Country Planning (TCP) department on zoning, the forest department, and the Mamlatdar on title and use. A 2026 amendment (Bill 8 of 2026, replacing an ordinance of 2025) cut the time limit for deciding an application from 60 to 45 days, with effect from 2 December 2025, but there is no deemed approval if the deadline is missed. If the land is not in a zone where your use is permitted, conversion will not be granted until the zone is changed under the TCP Act, a separate and more contested process. This guide explains the steps.
The two separate permissions
| Permission | Law | Authority | Question it answers |
|---|---|---|---|
| Zoning (and change of zone) | Goa Town and Country Planning Act, 1974 (including section 39A for change of zone) | TCP department and the Chief Town Planner | Is the land in a zone, such as settlement, where building is allowed? |
| Conversion sanad | Goa Land Revenue Code, 1968, section 32 | Collector or delegated officer | Can this land be used for non-agricultural purposes, and on what conditions? |
| Construction licence | Panchayat Raj Act or Municipalities Act, with TCP technical clearance | Panchayat or municipality | Can this specific building be built? |
A sanad does not replace the construction licence, and a construction licence is not valid without the land being correctly zoned and converted.
Step-by-step conversion
- Check the zone: obtain a zoning certificate from the TCP department, which states the zone of the survey number under the Regional Plan and any Outline Development Plan.
- Apply for conversion: to the Collector of North or South Goa with the survey plan, Form I & XIV, title documents, zoning certificate and site plan showing the area to be converted.
- Reports: the Collector calls for reports from the Mamlatdar (title, possession, tenancy), the forest department (whether the land is forest or private forest) and others where relevant, such as CRZ or water resources.
- Site inspection: officials may inspect the plot.
- Conversion fee: payable on the area converted at rates that depend on the use and location; the order states the amount.
- Sanad: issued with conditions, such as setbacks, use, and the time to start construction.
The 2026 change: 45-day time limit
The Goa Land Revenue Code was amended to require a decision on a conversion application within 45 days instead of 60. The change was first made by an ordinance in late 2025 and then by Bill 8 of 2026, deemed to have come into force from 2 December 2025. The amendment does not provide that an application is deemed approved if the authority does not decide in time. If your application is delayed, follow up in writing and, where needed, approach higher authorities or the court for a direction to decide.
Change of zone under section 39A
If the land is in a zone where your use is not allowed (for example, orchard or agricultural land where you want a house), you need a change of zone under section 39A of the TCP Act and the rules made in 2024. Applications are scrutinised, published for objections, and decided by the TCP Board or government. Fees are charged per square metre, with higher rates above certain areas; reported figures differ between sources, so confirm the current schedule with the TCP department. Changes of zone have been heavily debated in Goa and challenged in court, so a buyer should not pay a full price for land on the assumption that a zone change will be granted.
Why applications are rejected or delayed
- Wrong zone: the land is in a no-development, orchard, natural cover or eco-sensitive zone.
- Forest or private forest: the forest report identifies tree cover meeting the criteria.
- Tenancy or mundkar claims: the Mamlatdar’s report shows a tenant or mundkar; see our guide to mundkar rights in Goa.
- Title gaps: heirship or partition not complete; see our guide on inventory proceedings in Goa.
- CRZ: land within coastal regulation zones; see our guide to CRZ rules for Goa properties.
- Access: no legal access road of the required width.
Example
A family in Assagao owns a 1,200 sqm plot shown as settlement zone in the Regional Plan, with a small orchard portion. They get a zoning certificate, apply for conversion of the settlement portion only, and attach the survey plan marking the area. The forest report finds no forest cover. The Mamlatdar confirms there are no tenants. The Collector grants the sanad within the time limit on payment of the conversion fee, and the family then applies to the panchayat for a construction licence for a single villa. They do not build on the orchard portion.
Tax and accounting points
- Conversion of land held as a capital asset into stock-in-trade (for example, by a developer) is a taxable event under the income-tax rules on conversion, with tax due when the stock is sold; plan this with your CA.
- Conversion fees are part of the cost of the land for capital gains or business accounts.
- GST does not apply to conversion fees paid to the government in its sovereign capacity.
Buyer’s checklist
- Zoning certificate under the current Regional Plan and any ODP.
- Conversion sanad, its conditions and the area covered.
- Form I & XIV showing no tenant or mundkar entries.
- Forest status and CRZ map check.
- Approved construction licence, if a house is already built.
FAQs
Who grants a conversion sanad in Goa?
The Collector of the district, or the officer to whom the power is delegated, under section 32 of the Goa Land Revenue Code.
How long does conversion take in Goa?
The law now requires a decision within 45 days of a complete application, though there is no deemed approval if that is missed.
Can I convert agricultural or orchard zone land?
Not directly; a change of zone under the TCP Act is needed first, and it may be refused.
Is a conversion sanad enough to start building?
No. You also need a construction licence from the panchayat or municipality.
TAXAJ, with its legal team in Goa, helps buyers and owners check zoning, apply for conversion and plan the tax on land. Talk to our Goa team.
Last updated 11 November 2026. Sources: Goa Land Revenue Code, 1968, section 32, as amended by the Goa Land Revenue Code (Amendment) Bill (Bill 8 of 2026) replacing Ordinance 5 of 2025; Goa Town and Country Planning Act, 1974, section 39A and the change-of-zone rules of 2024. The example is illustrative. General information only; confirm current fees with the authorities.